Futur Health Lab
Site
Dubai MedCity
Project Type
Medical laboratory
Project Description: A medical cell lab company wanted to establish a medical lab affiliated with them in Dubai Medical City, and the project was critical due to the urgent need to complete the project in full within a period not exceeding 90 days from the start date.
We started with the owner from the beginning of the contract with the contractor, and a meeting was held during the first week to determine the work method and communication.
During the execution phase:
Assigning a work team consisting of 3 engineers (civil project manager, mechanical project manager, planning and budget engineer)
Visits at an average of 3 times a week
35 inspection reports
Total of 18 weekly reports
Total of 8 final inspection reports
Total of 22 site meetings with the contractor and the owner
Countless calls and discussions with the owner
Countless correspondences on the project's WhatsApp group, which includes our team, the contractor, and the owner
More than 90 emails
Settling 6 requests for additional work and providing 20% of the required amount while maintaining the contractual time frame
Receipt status:
Number of delay days zero
Number of technical problems after receipt by the owner zero
Full satisfaction from the owner with the quality of the provided service